Montville's Waughaw Valley Trail Is Open. The Signs, Map and Parking Are Next.

At 620 Main Road, a gravel path heads away from Route 202 and into the woods behind Towaco Center. It crosses several creeks on bridges, has benches where the grade gives you a reason to stop, and has security cameras along the way. It runs 1.31 miles to a second trailhead near Abbott Road. TAPinto Montville reported that people had been walking it for a couple of months before the Township held a formal ribbon cutting at 5 p.m. on Tuesday, Aug. 18, 2026.

The trail is finished enough to walk. The things you only notice once you're out there are still on the way: mile markers, a trail map, and maybe a parking area that holds up in wet weather. The signs and map are moving through Montville's Township Committee this fall, and graveling the parking area has been raised for a future meeting, so the Waughaw Valley Trail you walk in November is an early version of the one it will become.

Twenty-Five Years From Purchase to Ribbon

The pace makes more sense once you see the whole timeline. According to TAPinto's account of the opening, Montville bought the land in 2001 with Open Space funds. Design work was supported by a $73,000 grant from the New Jersey Highlands Council. Construction came mostly from the Morris County Trail Construction Grant Program, which put in more than $530,000 of the project's roughly $648,000 total cost.

Milestone What happened Source
2001 Land acquired with Montville Open Space funds TAPinto, Aug. 18, 2026
2014 Morris County Trail Construction Grant Program begins TAPinto, Aug. 18, 2026
Design phase $73,000 NJ Highlands Council grant TAPinto, Aug. 18, 2026
Construction More than $530,000 from the county program, about $648,000 total TAPinto, Aug. 18, 2026
Summer 2026 Trail walkable before the formal opening TAPinto, Aug. 18, 2026
Aug. 18, 2026 Ribbon cutting at 620 Main Road TAPinto; Montville Township
Sept. 8, 2026 Open space ordinances for signage and trail maintenance introduced Township Committee minutes
Sept. 22, 2026 Open Space Committee working on a Waughaw Valley Trail map Township Committee minutes

Morris County Commissioner Thomas Mastrangelo, a longtime Montville resident, put the county's share in context at the ceremony. "The trail construction program started in 2014. Since then, we've funded $7.8 million in trail construction," he told the crowd, as TAPinto reported. "This is what makes Morris County great. Between our open space and our trails, this is what Morris County is about."

Measured against that $7.8 million countywide, the roughly $530,000 for Waughaw Valley is a large share of what the program has spent in 12 years. That kind of money buys bridges over creeks and a graded gravel bed, the expensive and hard-to-redo parts of a trail. The work left to do is smaller in cost, but it's the part a walker deals with every visit.

Parking at the Main Road End

The Main Road trailhead has the most detail on record, and parking there needs some care. In its opening coverage, TAPinto said trail visitors should use the designated grassy area next to the trailhead. The paved lot for Vervain/Mile High Physical Therapy belongs to that business and is not meant for trail parking.

The grass is the problem. TAPinto reported that the grass lot can get waterlogged after wet weather. It said the Township Committee might take up adding a gravel layer at a future meeting to improve traction and access.

The ground was already a factor before the ceremony. In an Aug. 6 notice on the Township website, Montville asked ribbon-cutting guests to park in the NJ Transit lot across the street because the trail site was wet. NJ Transit's Towaco Station page puts the station on Route 202 and lists Lot 1 at Main Street and Waughaw Road. That arrangement was made for one event. It is not a standing trail parking agreement, and NJ Transit notes that its parking information can change without notice.

For an ordinary weekend walk, here is what's on record so far:

  1. Park on the grassy area beside the 620 Main Road trailhead.
  2. Stay out of the paved Vervain/Mile High Physical Therapy lot.
  3. After rain, expect the grass to be soft or waterlogged.
  4. Check the Township's meeting minutes for any decision on graveling the lot.

The minutes from the Aug. 18 Committee meeting note the trail's grand opening but list no parking action. The Oct. 13 agenda has no separate parking item either. Any change will appear in the Montville Agenda Center, where the Township posts Committee agendas and minutes, including for the Oct. 27 regular meeting.

At the other end, the opening coverage places the second trailhead only "near Abbott Road." The published accounts give no street address or parking instructions for that end, so most first-time visitors will start from Main Road.

Signs, Mile Markers and a Map

Wayfinding is where the trail is still being built. Mile markers would tell you how far you've walked toward the Abbott Road end, and a map would show both trailheads before you leave the car.

At the Sept. 8 Township Committee meeting, according to the minutes, Administration introduced two open space ordinances, one for open space location signage and one for trail maintenance. Both name the Waughaw Valley Trail and the Metro Tract. At the same meeting, Committee member Senaldi reported that the Recreation Commission expects signage for the Waughaw Trail, including mile markers.

Two weeks later, the Sept. 22 minutes recorded that the Open Space Committee is working on a Waughaw Valley Trail map. The same report covered an Eagle Scout project, a request for blue trail maintenance at Camp Dawson, and plans for a pollinator planting at 103 Horseneck Road.

Taken together, those entries show the trail moving from a construction project into regular upkeep. A maintenance ordinance means someone is assigned to care for the trail after the grant money is spent. Mile markers on a 1.31-mile path let you plan a loop to the second bridge and back, or time an out-and-back before dark, which matters once November evenings start before 5 p.m. When the map is published, it should appear on the Township's Open Space Trails & Maps page, where Montville posts maps for its preserved land.

Mayor Frank Cooney described the goal at the ribbon cutting, as TAPinto reported. He called it "a 1.31-mile gravel trail with bridge crossings, designed to provide residents and visitors with a safe and enjoyable way to walk, hike, and bike through this beautiful part of our community," and said "the trail provides an important connection around Route 202 and the Towaco Center area." The signs and map are how that connection becomes easy to find for someone who didn't attend the ceremony.

Dog and leash rules, trail hours and any planned extension have not been spelled out in the opening announcements or the Committee minutes. Those details may arrive with the signage.

Coffee Before, Breakfast After

Because the trail runs along Route 202 near Towaco Center, it's easy to pair a walk with a stop on Main Road.

  • Overflow Coffee Co., 9 Main Rd., Ste. 300. The newest option in the corridor. Montclair Girl's fall 2026 new-business roundup reported that the café held its grand opening in September 2026 with a ribbon cutting, a BBQ, live music, face painting and giveaways. Overflow's website lists its menu, hours, online ordering and pickup.
  • Red Barn Restaurant, 446 Main Rd. #5, Towaco. Red Barn's site lists breakfast, lunch and dinner service. For a morning walk, it means a full breakfast is close by.

Both are on the same stretch of Main Road the Mayor called the Route 202 and Towaco Center connection, so the trail and the businesses along it serve the same short trip. Check posted hours before heading out, since business websites change.

If You Walk It This November

The trail open now has its bridges, benches and cameras, and the work that took 25 years and about $648,000 is done. Still to come are mile markers, a map and possibly a gravel parking surface, all at the stage of ordinances, committee work and agenda items. Start at 620 Main Road, park on the grass, and expect soft ground after rain. The Agenda Center minutes will be the first public record of the next step.

If you live near Towaco Center and want to know how new amenities like this one show up in your home's value, Francesca Messercola and the team are glad to talk it through. Ask us for a free home valuation and we'll walk you through what we see on your street.

Ready to Buy, Sell, or Invest? Let’s Get Started!

From market analysis to negotiation and closing, I offer a full-service approach with one goal in mind: your success. No two clients are the same, and that’s why I tailor every strategy to fit your unique needs.

Follow Me on Instagram